1、小(xiao)微工程(cheng)5個工作日;
2、用(yong)戶產權內(nei)(nei)配套管(guan)線施工(gong)(gong)(gong)完(wan)(wan)成(cheng)后(紅(hong)線內(nei)(nei)燃氣(qi)(qi)工(gong)(gong)(gong)程已安裝(zhuang)完(wan)(wan)成(cheng)),自用(yong)氣(qi)(qi)申報(bao)起,在完(wan)(wan)成(cheng)外(wai)線施工(gong)(gong)(gong)后,4.5個工(gong)(gong)(gong)作(zuo)日內(nei)(nei)完(wan)(wan)成(cheng)接(jie)駁供(gong)氣(qi)(qi)。
3、用戶(hu)紅線(xian)外無配套燃氣(qi)管(guan)線(xian)或既有配套管(guan)線(xian)不能滿足用戶(hu)需求,需要新敷設燃氣(qi)配套管(guan)線(xian)的(de)安(an)裝工程,現(xian)場具備安(an)裝條件的(de)自用戶(hu)用氣(qi)申請至供氣(qi)時限原則不超(chao)過11個工作日(不包(bao)含道路挖掘等(deng)行政(zheng)審批時限)。